Case Study (Civil Subbie) (2026): Winning a $220k Job but Stalling at Pre-Start

Civil subcontractor funding case study for tradies and civil contractors | Switchboard Finance

🧱 civil subbie · mobilisation · plant · sequencing · 2026 · Tradie Hub
Case Study (Civil Subbie) (2026): Winning a $220k Job but Stalling at Pre-Start — How We Funded Mobilisation + Plant Without Enquiry Damage

This happens more than people admit: you win the job, you sign the start date, then you stall at pre-start because mobilisation cash and plant deposits land at the same time. The goal wasn’t “more debt.” It was clean sequencing, minimal credit noise, and a pack that made the lender say “yes” fast.

If you’re in the civil/tradie corridor, start with Tradie Finance Australia. If your priority is approval speed on plant, the direct lane is Low Doc Asset Finance.


1) The situation (why a “good job” still stalls)

A civil subcontractor won a $220,000 package on a tight pre-start timeline. The issue wasn’t profit — it was timing. Mobilisation costs hit first, but the first meaningful progress claim was weeks away.

What needed funding (pre-start)
  • Mobilisation: inductions, traffic control setup, initial materials, labour ramp, fuel/transport
  • Used plant upgrade: reliable machine to meet the program (and avoid hire blowouts)
  • Goal: avoid scattered applications (and the “enquiry damage” spiral)
Real-life example: Their site start was locked for Monday. Without the initial mobilisation spend, the job could be “won” but still lost — because the program would slip before week one.

2) The numbers (simple, lender-readable)

The lender didn’t care about the story — they cared about whether the job cashflow could carry the commitments, and whether the bank conduct showed control. So we turned it into a one-page snapshot.

Line Number Why it mattered
Contract value $220,000 Proves revenue and timing (not “maybe work”)
Job duration 8 weeks Shows turnover pace + how fast cash returns
Upfront mobilisation window 14 days This is where stalls happen (cash out before cash in)
Mobilisation cash need $38,000 Enough to hurt, not enough to justify a messy facility
Used plant purchase $135,000 Main asset funding decision
Expected plant deposit (budget) ~10% Deposit risk needed controlling
Cash buffer target $15,000 Stops “overdraft chaos” on Bank Statements

3) The sequencing (how we avoided enquiry damage)

We ran a “one story, two-step” approach: cover mobilisation first without throwing hard enquiries everywhere, then place the plant once the pack was clean and the story was consistent. The point was to protect the Credit File while still moving fast.

Two-step plan (in plain English)
  • Step 1: a short, controlled buffer for mobilisation (keep it tight and purpose-led)
  • Step 2: plant approval once the invoice + condition pack was ready (single lane, no shopping)
  • Rule: no scattergun applications → no unnecessary Hard Enquiry noise
Consequence if you ignore this: you end up with multiple enquiries, inconsistent limits, and a lender that assumes “distress” — which usually forces deposits and slows everything down.

4) What the lender actually cared about (decision points)

The lender’s “yes” wasn’t emotional. It came down to three boxes: conduct, story, and asset confidence. We built the submission around those exact boxes.

The 3 decision boxes
  • 1) Conduct: clean Bank Statements (no chaos, no constant reversals, no unexplained spikes)
  • 2) Story: the cash timing explained as a Facility purpose (mobilisation → first claim → stabilise)
  • 3) Asset confidence: clear plant IDs and condition support so valuation doesn’t trigger an LVR haircut

If you want the most direct approval lane for the plant side, start at Low Doc Asset Finance. If you need a buffer facility that doesn’t wreck the rest of your file, start at Working Capital Loans.

For broader context on cashflow warning signs (the “why this happens”), see 5 Cash Flow Warning Signs Your Business Needs a Finance Safety Net.

Summary

The job wasn’t the problem — timing was. We funded mobilisation first with a controlled, purpose-led facility, then placed the used plant with a clean invoice and condition pack. The lender cared about conduct, a single coherent story, and asset confidence — not “how excited” the client was.

If you’re trying to start a job without credit noise, build your pack around the lender’s three boxes and keep the sequencing tight.

FAQ

Disclaimer: This content is general information only and isn’t financial, legal, or tax advice.

Previous
Previous

Western Melbourne Civil Contractor Checklist (2026)

Next
Next

Used Civil Plant Finance (2026): 12 Red Flags to Look out for