Development Finance
Capital stack · Senior debt · Intercreditor deed · The exit
Mezzanine finance fills the space between what a senior lender will advance and the equity a developer actually has. This guide explains where it sits in the capital stack, how a typical Australian stack splits in numbers, what it costs including the fees the headline rate hides, the security and intercreditor deed behind it, how it compares with preferred equity and the other options, what is negotiable on a term sheet, who qualifies, where to get it and what happens after you ask, and the risks.
Quick Answer
Mezzanine finance is a subordinated loan that sits behind senior construction debt and ahead of developer equity. It can close part of a property development funding shortfall without selling ownership, but it carries higher costs and repayment risk than senior debt. Indicative published ranges put the strip at 10 to 20 percent of total development cost and interest in the mid-teens to low twenties percent per annum, plus establishment fees commonly 2 to 4 percent; these are published ranges, not November 2026 offers. Most developers arrange it through a broker alongside the senior facility. Check whether the senior facility permits it, whether the feasibility survives delay and lower sales proceeds, and how both loans will be repaid. See the worked funding-gap example and delay stress test.
Also called: mezzanine debt, mezzanine loan, mezzanine financing, mezzanine funding.
| Topic | The short answer |
|---|---|
| What it is | A subordinated loan that sits between the senior facility and the developer's equity in the capital stack |
| What it is for | Topping up senior debt so the developer contributes less cash to the project |
| Typical size of the strip | Commonly 10 to 20 percent of total development cost, taking combined debt to roughly 75 to 90 percent of cost and about 75 to 80 percent of end value; indicative market ranges |
| The security | A second registered mortgage behind the senior lender, usually with a general security agreement and guarantees |
| The key document | The intercreditor deed with the senior lender, setting priority, standstill and cure rights |
| What it costs | Commonly mid-teens to low twenties percent per annum with interest capitalised, plus establishment fees commonly 2 to 4 percent of the limit; indicative only, varies by lender and project |
| How it is repaid | From settlements or a refinance once the project completes, after the senior facility is cleared |
| Regulation | Business-purpose credit sits outside the National Credit Act; commercial loans carry the lowest borrower protection |
| Where to get it | Private credit funds, specialist non-bank lenders and private lenders, usually arranged through a broker alongside the senior facility; see how we fund developments |
| What sets the speed | The senior lender's consent and the intercreditor deed, more than the mezzanine lender's own credit decision |
What is mezzanine finance?
Mezzanine finance is a subordinated loan that fills the gap between senior debt and equity in a funding structure. The name is the architecture: a mezzanine is the floor between two floors, and mezzanine finance is the layer between the senior debt at the bottom of the risk order and the owner's equity at the top of it. In Australian property development, where the instrument does most of its work, it tops up the senior construction facility so the developer's cash contribution shrinks, in exchange for a price well above senior debt and a repayment position behind it.
One definitional fork is worth settling immediately, because the term means two related but different things. In corporate lending, the version most international definitions describe, mezzanine is a hybrid instrument: unsecured or lightly secured subordinated debt that often carries an equity kicker such as warrants or a conversion right, with interest sometimes paid in kind rather than in cash. In Australian property development, the version this guide covers, mezzanine is almost always straight subordinated debt secured by a second registered mortgage, with a fixed coupon and no equity conversion, although a minority of lenders add a profit participation. Same position in the stack, different legal machinery. If a definition you have read mentions warrants and yours mentions mortgages, both are right; they are describing different markets.
That position in the stack is the whole economics. The capital stack is the ranking of every dollar in a project by who gets repaid first. Senior debt sits first, secured by the first mortgage and repaid before anyone else. Mezzanine sits second, secured behind it. Preferred equity, where it exists, sits third, and the sponsor's own equity sits last, first to absorb any loss and last to be paid. Subordination is what the mezzanine lender is pricing: they recover only after the senior lender has been paid in full, so they charge for standing in that queue. The table sets the two debt layers side by side.
| Factor | Senior debt | Mezzanine finance |
|---|---|---|
| Priority on repayment | First, paid before everyone | Second, paid after the senior lender in full |
| Security | First registered mortgage | Second registered mortgage, with senior consent |
| Share of the funding | The majority of the debt, commonly 60 to 70 percent of total development cost | A top-up strip, commonly 10 to 20 percent of total development cost |
| Pricing | Lower, priced for first-ranking risk; single digits to around 11 percent per annum in current published ranges | Higher, priced for subordination; commonly mid-teens to low twenties percent per annum |
| Interest during the build | Usually capitalised or drawn down | Almost always capitalised to the facility |
| Who provides it | Banks and non-bank construction lenders | Private credit funds and specialist non-bank lenders |
Sizing runs off value and cost. A senior construction lender advances against the project's end value, its gross realisation value (GRV, also called gross development value or GDV), and against total development cost (TDC), and stops well short of either. Mezzanine extends the combined debt higher up both measures, which is why it is often described as equity gap funding: it replaces part of the cash the developer would otherwise have to find, without giving away ownership the way a straight equity partner would. How the layer behaves in a commercial property capital stack follows the same logic as a residential project, with the income of the asset doing some of the work the sales schedule does in a build.
How does mezzanine finance work in a property development?
In practice, mezzanine is arranged alongside the senior facility and drawn as the project needs it, then repaid at the exit. The sequence runs like this: the developer secures a site and a development approval, the senior lender sizes its facility against end value and total cost, and the shortfall between senior debt plus available equity and the full project cost becomes the mezzanine strip. The two facilities are documented together, the senior lender consents to the second mortgage, and an intercreditor deed fixes the order between the lenders before the first drawdown. Our property development finance guide walks the whole funding structure from site to settlement; this section follows just the mezzanine layer.
The proportions vary by project, but indicative published Australian market ranges cluster tightly enough to put numbers on a typical stack.
| Layer | Share of total development cost | Indicative pricing | Security position |
|---|---|---|---|
| Senior debt | Commonly 60 to 70 percent of TDC | Commonly single digits to around 11 percent per annum | First registered mortgage |
| Mezzanine | Commonly 10 to 20 percent of TDC, taking combined debt to roughly 75 to 90 percent of cost and about 75 to 80 percent of end value | Commonly mid-teens to low twenties percent per annum, capitalised | Second registered mortgage, sometimes with share security |
| Preferred equity, where used | Commonly 5 to 10 percent of TDC | A preferred return plus, often, a profit share | No mortgage; unit or share security and control rights |
| Sponsor equity | Commonly 10 to 25 percent of TDC, with lenders wanting genuine cash or land equity of at least around 10 to 15 percent | The residual profit, and the first loss | Last claim on proceeds |
Every figure in that table is an indicative published market range, not a quote: individual lenders publish higher and lower, a strong sponsor prices below the band and a first project prices above it, and the whole grid moves with the cash rate and lender appetite. What does not move is the mechanics. Two of them distinguish the mezzanine layer during the build. First, the money is usually drawn progressively rather than in one advance, tracking the project's funding table. Second, the interest is almost never serviced monthly. A development site produces little or no income while it is being built, so mezzanine interest is capitalised, sometimes called rolled up interest: added to the loan balance and repaid with it at the end. That is also how the regulator describes the risk: development lending is negative cash flow lending, with interest paid from capital rather than income until the project completes.
The exit is the whole deal. Mezzanine is repaid from settlements as the completed stock sells, or from a refinance once the project is finished and revalued, and only after the senior facility has been cleared. Where sales run slower than the facility term, unsold stock is often refinanced with a residual stock loan, which in current published ranges commonly advances 60 to 70 percent of value at pricing well below mezzanine, repaying the construction debt and buying the developer time to sell. Combined gearing is usually expressed against total cost as a loan to cost ratio, and against end value as an LVR, and the mezzanine strip is sized inside both ceilings.
What are mezzanine finance interest rates and costs in Australia?
Mezzanine finance in Australia commonly costs mid-teens to low twenties percent per annum, with interest capitalised to the loan and establishment fees on top. Those figures are indicative only, as at July 2026, and the honest way to read the cost is blended: what senior plus mezzanine together do to the project's feasibility. Published mezzanine finance rates in Australia span wider than the central band, from around 12 percent for credentialed sponsors on strong projects to the mid twenties for first-time sponsors or higher-risk profiles. The rate on the mezzanine strip is only part of the picture. Because the strip is small relative to the senior facility, a high rate on a thin layer can still produce a workable blended cost, and because the interest is capitalised, the cost compounds quietly against the project's end value rather than showing up in a monthly payment. The components below are the ones a term sheet will price.
| Cost component | How it commonly works | What to watch |
|---|---|---|
| Interest rate | Commonly mid-teens to low twenties percent per annum, with published quotes from around 12 percent to the mid twenties; indicative, varies by lender, project and gearing | Priced off subordination, sponsor strength and presale cover |
| Capitalisation | Interest added to the balance monthly rather than serviced | The balance grows to completion, so time overruns compound the cost |
| Establishment fee | Commonly 2 to 4 percent of the facility limit, often capitalised too | Charged on the limit, not the drawn balance |
| Line or facility fee | An ongoing fee on the limit while the facility is open | Runs even when the strip is only partly drawn; worth negotiating a cap |
| Step-up rate | Commonly 2 to 4 percentage points per annum added if the project runs past its target completion date | Construction overruns are common; the step-up prices your delay risk |
| Minimum interest period | Some term sheets specify a minimum interest period even on early repayment | Check the written minimum and any early-exit charge |
| Profit participation, some lenders | A kicker commonly of 2 to 5 percent of project profit where used, triggered above a margin threshold | The trigger threshold matters as much as the percentage |
| The blended cost | Senior plus mezzanine averaged across the whole debt stack | The number the feasibility actually has to wear |
| Legal and valuation costs | Borrower usually pays both lenders' documentation costs | The intercreditor deed adds legal work on both sides |
Those components stack. A facility quoted at a mid-teens headline rate can carry an all-in effective cost several points higher once the establishment fee, any line fee and any profit participation are counted, which is why the number to price is the blended feasibility cost, not the coupon. Time is the other quiet multiplier: on a $1 million strip at an indicative 18 percent per annum capitalised monthly, six months of delay at the end of an 18-month program adds roughly $122,000 to the balance before any step-up rate is triggered, because the interest compounds on interest already capitalised.
| Loan term | Interest accrued | Balance owing at exit |
|---|---|---|
| 6 months | About $93,000 | About $1.09 million |
| 12 months | About $196,000 | About $1.20 million |
| 18 months | About $307,000 | About $1.31 million |
| 20 months | About $347,000 | About $1.35 million |
| 24 months | About $430,000 | About $1.43 million |
Illustrative arithmetic only, not a quote, an offer or an approval indication. Establishment fees, line fees, legal and valuation costs, step-ups and any profit participation sit on top.
From Switchboard's deal flow
Basis: recent broking quotes and lender term sheets seen in Switchboard deal flow, as at July 2026. Indicative only, never a quote or an offer.
- Senior construction debt commonly sits around 60 to 65 percent of end value in current non-bank term sheets; mezzanine typically tops combined debt up to roughly 75 to 80 percent of value, and higher against cost. It varies by lender, project and presale cover.
- Mezzanine pricing is where this commonly lands: mid-teens to low twenties percent per annum, interest usually capitalised to the facility rather than serviced monthly, with establishment and line fees on top. The blended cost of senior plus mezzanine is what the feasibility has to wear.
- Above mezzanine, preferred equity trades a fixed rate for a profit share and control rights, including step-in on default. That is a different bargain, not a cheaper one.
Indicative only, from broking experience as at July 2026, not a quote, an offer, a rate you will get or an approval likelihood. Every figure varies by lender, project, gearing, presale cover and market conditions. Pricing on a live deal is a term sheet conversation, not a table.
What has changed for mezzanine pricing since July 2026?
The ranges on this page come from a July 2026 survey, and the money market has moved since. The Reserve Bank announced a rise in its cash rate target to 4.85 percent on 3 November 2026, effective 4 November, up 0.25 percentage points from the immediately preceding 4.60 percent setting, and its statement notes that housing prices have fallen significantly, which puts more weight on the end value test. This is not a mezzanine lending rate and does not mean every private-credit coupon increased by the same amount. Floating-rate senior loans and private-credit pricing respond differently depending on their benchmarks, margins and terms. Treat the bands as a starting point, ask every lender for current pricing in writing, and run the stress test on end value before you rely on the base case.
Published Australian development lending materials reviewed for this guide describe headline mezzanine ranges still clustered in the mid-teens to low twenties percent per annum, with weaker projects quoted into the mid twenties and above, establishment fees of 2 to 4 percent and profit participation of 2 to 5 percent where used. Many of those pages were dated before the November rise and their ranges disagree with each other, which is the clearest sign that a published band is a guide, not a price. Indicative only, never a quote.
Whether the cost is worth paying is a feasibility question, not a rate question. Mezzanine makes sense when the profit released by starting now, at a higher combined LVR, beats the profit of waiting until the developer has more cash, and it stops making sense the moment the blended cost eats the margin the project was built on. A rough discipline seen across the market: projects showing profit on cost in the low twenties and above tend to carry mezzanine comfortably, projects under the high teens tend to find the layer eats the reason for doing the deal, and the band between is where the modelling earns its keep. If you want that arithmetic run against a real project, start with a conversation rather than a calculator.
| Where the project sits | What mezzanine usually does | What to do next |
|---|---|---|
| Profit on cost in the low twenties percent or more | Usually carries the blended cost comfortably | Price the delay case, then compare mezzanine against an equity partner |
| Profit on cost in the high teens to low twenties | Works only if the modelling holds | Stress the feasibility at 5 and 10 percent below end value before signing |
| Profit on cost below the high teens | Tends to eat the reason for doing the deal | Look at stretch senior, more sponsor equity or a joint venture |
| No development approval yet | Not fundable as development mezzanine | Fund the approval stage first, then come back with the approval issued |
Can mezzanine close a development funding shortfall?
Mezzanine can help close a defined development funding gap when senior debt and genuine sponsor equity do not cover the remaining project cost, but only if both lenders accept the structure and the stressed exit can repay both loans. The first question is not how much a mezzanine lender will advertise. It is how much is actually missing after checking total development cost, senior facility limit, equity already invested, interest reserves and timing of drawdowns.
| Funding item | Illustrative amount | What it means |
|---|---|---|
| Total development cost used for this example | $6,000,000 | Assumed base project budget before the incremental mezzanine financing charges shown below |
| Senior facility | $3,900,000 | 65% of the example budget, assumed not approved by any real lender |
| Sponsor equity available | $1,300,000 | Cash and accepted land equity, assumed verified |
| Funding gap | $800,000 | Possible mezzanine principal if lender capacity and cashflow permit |
| Combined senior plus mezzanine principal | $4,700,000 | 78.3% of the $6 million example budget before accrued interest and fees |
| Mezzanine interest after 18 months | About $246,000 | Assumes $800,000 fully drawn on day one at 18% p.a., compounded monthly, with no repayments |
| Example establishment fee | $16,000 | Illustrative 2% of the mezzanine limit, excluding other costs |
Important: the $800,000 closes only the initial example gap. If the $6 million project budget has no allowance for the additional interest, fees, contingency and possible overruns, the true funding need may be larger. The example excludes senior interest, lender legal fees, valuations, tax, sales costs, repayment timing and any unused line fees. A lender will run a monthly sources-and-uses cashflow, not simply add three headline figures.
How do lenders calculate loan-to-cost, loan-to-GRV, peak debt and cash to complete?
Loan-to-cost (LTC) measures debt against qualifying development costs; loan-to-GRV measures debt against the expected gross realisation value. Peak debt is the maximum forecast loan balance including relevant draws, rolled-up interest and charges. Cash to complete is the cash still required to finish the project after allowing for confirmed available funding. Lenders may impose separate limits on each measure, and their definitions of eligible costs and debt differ.
| Test | Calculation | Interpretation |
|---|---|---|
| Principal LTC | $4.7m ÷ $6m = 78.3% | Senior plus mezzanine principal against the illustrative base cost; not a lender's approved combined facility test |
| Principal to GRV | $4.7m ÷ $8m = 58.8% | Assumes an $8m gross realisation value; sales costs and GST treatment need separate review |
| Mezzanine at month 18 | $800,000 + ~$246,000 interest + $16,000 establishment fee = ~$1.062m | Assumes the fee is payable at exit but does not itself compound; actual facility documentation may differ |
| Illustrative combined balance | $3.9m senior principal + ~$1.062m mezzanine = ~$4.962m | Excludes senior interest and fees, so this is not a fully modelled peak-debt number |
| Cash to complete | Remaining approved project uses minus confirmed available undrawn funding and usable equity | Requires a month-by-month sources-and-uses schedule; the example alone cannot determine it |
Why the $800,000 gap can become larger: if the $6 million budget excludes the roughly $262,000 of illustrative mezzanine interest and establishment fee, the project needs that amount funded from a facility reserve, additional sponsor cash, operating cashflow or another approved source. Borrowing those charges can also raise the lender's measured peak debt and gearing. Do not assume $800,000 of approved principal is $800,000 of spendable construction funds.
Does land equity count? A lender may recognise contributed land equity, typically after testing the land's acceptable current value, acquisition history, prior encumbrances, tax and transaction costs, and the amount of genuinely unencumbered owner interest. An unrealised valuation uplift is not automatically equivalent to available cash. See how development lenders test feasibility and the full development finance structure.
What if the senior lender will not allow mezzanine?
Do not sign a second facility in the hope that the title office will register it. Ask why the senior lender objects: combined leverage, documentation, further-advance priority, its own credit policy or the proposed mezzanine lender. Then test a single stretched senior facility, additional equity, a joint-venture contribution, a separate security property or a smaller project scope. A second mortgage being legally registrable in a state is not permission to breach a senior facility covenant. See the distinction between registration and consent in NSW.
Is mezzanine cheaper than an equity partner? Not automatically: compare the dollar cost and the control cost on the same project. The worked comparison sits in the alternatives section, alongside the joint venture guide.
What security does a mezzanine lender take?
A mezzanine lender typically takes four things: a second registered mortgage over the project land, a general security agreement over the borrowing company, personal or directors' guarantees, and an intercreditor deed with the senior lender. The second mortgage over the project land is the core security, registered on title behind the senior lender's first mortgage. The senior lender generally needs to approve additional development borrowing under its facility documents, and its cooperation is important to the intercreditor deed. However, title-registration rules and contractual consent are distinct: a second mortgage may be registrable without prior-lender consent in some jurisdictions, while still breaching senior loan covenants. Have a property solicitor check the state title rules and first mortgage terms before proceeding. See the NSW consent explanation. This is also where the Australian structure parts ways with the American one: in the United States, real estate mezzanine is typically secured by a pledge of the ownership interests in the entity that holds the property, not by a mortgage on title, so if you are reading US material, the enforcement mechanics it describes do not map onto an Australian deal.
Around the mortgage sit the supporting layers. A general security agreement, a GSA, takes security over the borrowing company's other assets and is registered on the Personal Property Securities Register, the PPSR, so the mezzanine lender's interest is visible to anyone who searches the company. Personal or directors' guarantees from the sponsors reach past the project company to the people behind it; guarantee caps may be negotiable depending on the lender and deal, and an uncapped guarantee is worth pushing back on. Some structures add security over the shares in the development company, which gives the lender a path to take control of the company itself rather than just the land; where that share security is ever enforced, the change of control can trigger landholder duty in some states, and caveat procedures, where a caveat supplements the pack, run on state-based lapsing rules, which is one more reason the documents need a development-experienced solicitor rather than a generalist.
Then comes the document borrowers keep asking about and almost no lender page explains: the intercreditor deed, sometimes called a deed of priority. It is the contract between the senior and mezzanine lenders that fixes how the two coexist, and its terms matter to the developer even though the developer is barely a party to the bargain. The table below splits what it protects on each side.
| Right or control | Who holds it | Why it matters to the developer |
|---|---|---|
| Absolute first-ranking priority over the project proceeds | Senior lender | The senior facility is repaid in full before the mezzanine lender or equity receives money |
| Standstill periods against mezzanine enforcement | Senior lender | The mezzanine lender may be blocked from acting while the senior lender decides how to respond to a default |
| Payment blocks during a senior default | Senior lender | Cash that would otherwise go to mezzanine can be frozen until the senior position is protected |
| Consent rights over the second mortgage and caps on further senior advances | Senior lender | The senior lender can decide whether mezzanine can exist behind them and how much priority debt can sit ahead |
| Control of enforcement and sale process | Senior lender | If the project fails, the senior lender usually controls the timetable and recovery path |
| A registered second mortgage rather than an unsecured promise | Mezzanine lender | The mezzanine lender gets a real title position, but only behind the first mortgage |
| Cure rights and sometimes buy-out rights | Mezzanine lender | The mezzanine lender may be able to fix a senior default, or buy out the senior debt, before enforcement progresses |
| A defined ranking and share of proceeds | Mezzanine lender | The deed sets what the mezzanine lender can recover after the senior lender has been cleared |
| Information and consent rights over material project changes | Mezzanine lender | Major changes to the build, budget, sales or facility can require lender consent, which can slow decisions |
| Step-in mechanics after a mezzanine default | Mezzanine lender | A default can shift practical control away from the developer and into the lender process |
For the developer, the practical reading is this: a default under either facility can put the whole project into the hands of the lenders' deed, and the timetable in that deed, who may act, and when, and who gets paid what, was negotiated between the lenders. Where the senior lender would rather not share the title at all, the alternative is often a single stretched facility instead of two layers; our note on stretched senior debt on a development site covers when that trade is available and what it costs.
How fast can you get mezzanine finance, and what slows it down?
Mezzanine finance is fastest when the senior lender has agreed in principle to a second mortgage, the intercreditor deed is on that lender's standard form, and the approval, building contract and presales are ready before you ask. There is no standard timeline, because settlement waits on whichever step finishes last, and that is usually the senior lender's consent and the deed rather than the mezzanine lender's own credit decision. The mezzanine lender's own decision may not be the slowest part; the steps around it are, and the table sets out who has to act on each one and what usually holds it up.
| Step | Who has to act | What usually holds it up |
|---|---|---|
| Credit assessment and feasibility re-run | The mezzanine lender | A feasibility that does not survive the lender's own end values and costs, or an exit that is described rather than evidenced |
| Valuation and quantity surveyor report | The lender's valuer and quantity surveyor | Site access, an "as if complete" valuation, or reports ordered by someone else that the lender cannot rely on |
| Senior lender consent | The senior construction lender | Its own credit approval of the request for a second mortgage behind its facility |
| Intercreditor or priority deed | Both lenders and their solicitors | Negotiation of standstill periods, cure rights, payment blocks and the cap on senior advances |
| Security and guarantee documents | The borrower's solicitor, the directors and any guarantors | Signing authority in the company or trust, and guarantors who are not available to sign |
| Conditions before the first drawdown | Both lenders | Presale evidence, the fixed-price building contract, insurances and the senior facility's own conditions |
What makes a fast mezzanine deal possible is preparation done before the mezzanine terms are signed. A senior lender that has agreed in principle to a second mortgage behind its facility removes the biggest unknown, and an intercreditor deed on that lender's standard form leaves less to negotiate. On the senior side the deed is often the longest step, and our guide to putting a second mortgage behind a construction loan sets out how long a deed of priority takes to negotiate. Having the development approval, the building contract and the presale evidence ready at the start means the drawdown conditions are met, not chased. And where one lender will hold the whole strip, a single stretched facility removes the deed altogether. Our property development finance guide sets out the senior facility timeline the mezzanine has to fit inside.
How does mezzanine compare with preferred equity, stretch senior, a second mortgage and a caveat?
The short version: mezzanine is secured subordinated debt with a fixed rate, preferred equity is profit-share equity with control rights, stretch senior folds the whole strip into one higher-geared facility, and a second mortgage or a caveat does similar work outside a construction stack. Five instruments compete for the same job, closing the gap between senior debt and equity, and they are not interchangeable. They differ in legal form, in security, in how they price, and in what happens when something goes wrong. Scattered comparisons of these pairs exist across our shorter notes; this table is the one place they sit side by side.
| Instrument | Legal form and ranking | Typical security | How it prices | Where it fits |
|---|---|---|---|---|
| Mezzanine finance | Subordinated debt, behind senior, ahead of all equity | Second registered mortgage, GSA, guarantees, intercreditor deed | Fixed rate well above senior, commonly mid-teens to low twenties percent per annum, interest usually capitalised | Topping up a development or acquisition stack without giving up ownership |
| Preferred equity | Equity with a preferred return, behind all debt, ahead of sponsor equity | No registered mortgage in most structures; share or unit security and control rights | Preferred return plus, often, a profit share; step-in on default | Larger raises where debt ceilings are full; see preferred equity compared with mezzanine debt |
| Stretch senior | One senior facility written to a higher gearing, no second lender | First registered mortgage only | A single blended rate above vanilla senior, below mezzanine | When one lender will hold the whole strip; simpler documents, one relationship |
| Second mortgage | Debt secured behind an existing first mortgage on a completed property | Second registered mortgage with first mortgagee consent | Priced between senior debt and mezzanine, term-loan style | Releasing equity from property you already own; see our second mortgage guide |
| Caveat funding | Short-term debt noted on title by caveat, not a registered mortgage | A caveat over the property | Fast, short and expensive relative to term | Very short funding needs measured in weeks; see our caveat loans guide |
The line that trips people most is mezzanine versus preferred equity, because the two often raise a similar amount in a similar deal. The clean split is legal nature: mezzanine is debt with a mortgage and a fixed cost; preferred equity is equity with a return hurdle, usually a profit share, and control rights instead of security. A stretch senior facility removes the second lender entirely by writing one facility to a higher gearing, which simplifies the documents at a blended price. A straight second mortgage does mezzanine-like work on a completed property rather than a construction project, and a caveat is the short-fuse tool at the edge of the family. Most of these sit within the broader private lending market rather than with banks.
Which leaves the developer with more profit: mezzanine, stretch senior or JV equity?
The cheaper-looking percentage is not enough to identify the better structure. Compare the extra financing's dollar cost, the developer's remaining profit, ownership and voting rights, personal guarantees and downside liability on the same project. The example below isolates the cost of raising an additional $1 million over 18 months; it is not a quoted deal or a complete development feasibility.
| Structure | Illustrative incremental funding cost | Developer retains from $1.5m hypothetical pre-incremental-funding profit | Main non-price trade-off |
|---|---|---|---|
| Mezzanine loan | 18% p.a. compounded monthly on $1m fully drawn: ~$307,341 interest, plus assumed 2% fee ($20,000) | ~$1,172,659 | Subordinated debt still repayable regardless of realised profit; consent and guarantee risk |
| Stretch senior increment | Assumed 12% p.a. compounded monthly on the incremental $1m: ~$196,147 interest, plus assumed 1% fee ($10,000) | ~$1,293,853 | Only possible if a single senior lender actually approves the higher gearing and relevant whole-facility pricing |
| JV equity investor | Hypothetical 30% share of the $1.5m profit: $450,000 | $1,050,000 | Investor receives negotiated upside and potentially governance or decision rights; loss sharing varies |
Read the assumptions: the $1.5 million is an assumed project profit after common base-project costs but before the incremental funding arrangement compared here; it is not a GRV or guaranteed return. All $1 million of debt is assumed drawn on day one, compounded monthly, and repaid at month 18. The stretch senior example unrealistically holds other senior pricing constant to isolate the incremental cost; actual proposals can reprice the whole facility. The JV is assumed to share this same pre-financing profit without a fixed preferred return, fees or minimum payment. Taxes, GST, legal costs, staged drawdowns, changes to credit availability and downside guarantee exposure are excluded. The scenarios do not have equivalent risk or control rights, and an equity investor's return may instead be calculated on a different agreed profit base.
What if the project underperforms? Debt remains due under the facility even if the project loses money. A genuine equity partner generally bears negotiated equity downside but can hold approval or control rights. Model sales shortfalls and six-month delays under each proposed term sheet before comparing the developer's retained profit. Read the dedicated preferred equity versus mezzanine comparison and joint venture guide for the distinct legal structures.
Who provides mezzanine finance in Australia, and how do you check a lender?
Mezzanine finance in Australia is provided mainly by private credit funds, specialist non-bank lenders and private lenders such as family offices, with banks rarely taking a second-ranking position behind another lender's construction loan. Which class sits behind a term sheet shapes how the lender behaves when a project needs a decision or more time.
| Lender type | Where the money comes from | Who supervises it | What it changes for the developer |
|---|---|---|---|
| Private credit fund | Investor money pooled and lent by a fund manager | ASIC, through the manager's licence and, for a retail fund, its responsible entity | Appetite and terms follow the fund's mandate and its investors, and a fund under pressure can slow or shrink its answer |
| Specialist non-bank lender | Wholesale funding lines and securitisation | ASIC for conduct, no prudential supervisor | Policy follows the funding line, so terms move when the funder's terms move |
| Private lender or family office | Its own balance sheet | Often no credit licence, because business-purpose lending sits outside the National Credit Code | Decisions are made close to the money, and the protections sit in the loan documents |
| Contributory mortgage fund | Investors who choose the individual loans they are in | ASIC, through the responsible entity | Each loan needs investors to commit to it, loan by loan |
| Bank | Deposits | APRA and ASIC | Rarely ranks behind another lender's construction facility |
Checking a lender before you sign is quick. Search its licence, or its fund manager's, on the ASIC professional registers, and confirm on ABN Lookup that its ABN and entity name match the term sheet. A lender writing only commercial loans need not hold a credit licence or belong to AFCA, as ASIC's guidance on disputes about commercial loans sets out, so a missing licence is not a warning sign on its own, but the protection then sits in the documents. Ask who actually funds the loan, and whether that money is committed for the whole build. The same method used to check a second mortgage lender applies here, because the lender classes are the same.
ASIC's November 2026 follow-up review of private credit funds, Report 846, released 10 November 2026, found that many poor fee, disclosure and conflict practices identified a year earlier remain; it is about the funds and their investors, not borrower protection, but it is a fair reason to ask a fund lender how its loans are funded.
Where can you get mezzanine finance for your deal, and what happens after you ask?
Most developers get mezzanine finance through a broker who places it with a private credit fund, specialist non-bank lender or private lender, arranged alongside the senior construction facility so the senior lender can consent from the start. Going lender by lender is possible, but each one runs its own feasibility re-run and asks for the same pack, and a mezzanine offer means little until the senior lender has agreed to sit behind it. The fastest first step is the same either way: have the pack below ready before you ask for terms.
| Document | What the lender uses it for | The common gap |
|---|---|---|
| Development approval and endorsed plans | Confirms the project can be built as modelled | Approval still pending, or conditions not yet met |
| Feasibility showing total development cost, end value and profit on cost | The lender re-runs it on its own end values and costs | End values or costs with no evidence behind them |
| Building contract or quantity surveyor cost plan | Tests the build cost and the builder | No fixed price, or a builder the lender cannot check |
| Presale schedule | Evidences the exit and the senior lender's cover condition | Too few contracts, or contracts without deposits recorded |
| Senior lender's term sheet or indicative terms | Sizes the gap and starts the consent conversation | No senior lender yet, so the gap cannot be sized |
| Sponsor track record and company or trust structure | Prices delivery risk and sets who signs and who guarantees | No list of completed projects, or an unclear entity structure |
| Statement of assets and liabilities for each guarantor | Tests what the guarantees are worth | Guarantors not yet identified |
What happens after you ask for mezzanine terms?
- A first read of the feasibility. The broker checks whether the gap suits mezzanine, a stretched senior facility, a joint venture partner or more equity, before any lender sees the file.
- Indicative terms from more than one lender. The file goes to lenders writing second-ranking development debt, and the offers are compared on rate, fees, step-up, minimum interest period and guarantee cap, not on the headline rate alone.
- The senior lender is asked to consent. Raised early, because no mezzanine deal exists without first mortgagee consent and the deed that follows it.
- Credit approval and a term sheet. The mezzanine lender re-runs the feasibility and orders its own valuation and quantity surveyor report.
- Documents and the intercreditor deed. Solicitors for both lenders and the borrower settle the loan, the security, the guarantees and the deed.
- Settlement and first drawdown. Conditions precedent are met, the second mortgage is registered, and funds are drawn progressively against the funding table.
- During the build and at the exit. Progress claims are certified, variations may need lender consent, interest capitalises, and the facility is repaid from settlements or a refinance once the senior lender is cleared.
The most useful thing to know before the first call is your own profit on cost after a conservative re-run, because it decides which of those paths is open. If you want it read against your project, check your eligibility or talk to a broker.
Who qualifies for mezzanine finance, and what gets deals declined?
Construction-stage mezzanine most often suits developers with an approved project, a feasibility that survives blended financing costs, credible equity, an acceptable builder and a senior lender able to agree on the financing structure. Presale, approval and sponsor-experience requirements differ by lender and project. Lenders underwrite the project first and the sponsor a close second, and the criteria are more specific than most borrowers expect. The lender is being asked to hold the most exposed layer of debt in the deal, so they want the layers around them solid: a senior lender they can document with, a project that clears its numbers at the blended cost, and a sponsor who has delivered before. The table splits the file that gets funded from the file that does not.
| Underwriting factor | Fundable file | Decline risk |
|---|---|---|
| Development approval | A development approval is in place, not pending | No development approval for a proposed construction-stage facility, or uncertainty about approval timing |
| Senior lender consent | The senior lender is open to consenting to the second mortgage and intercreditor deed | No realistic path to first mortgagee consent |
| Sponsor equity | Genuine sponsor cash or arm's-length land equity sits behind the ask | Thin genuine sponsor equity, or reliance on paper uplift only |
| Feasibility | The feasibility still works after the blended senior plus mezzanine cost | The feasibility only works if end values, build costs and sales timing all land perfectly |
| Presales | Presales satisfy the senior lender's cover condition | Presale cover falls short of what the senior facility requires |
| Builder | A fixed-price building contract is signed with a builder who checks out | The builder is unresolved, undercapitalised, untested or not fixed-price |
| Sponsor experience | The sponsors have delivered comparable projects before | First-time delivery risk is being pushed onto the most expensive layer of debt |
The market puts rough numbers on most of those lines, all indicative and all lender-specific. Genuine sponsor equity commonly needs to reach at least around 10 to 15 percent of total development cost, in cash or arm's-length land equity, before a mezzanine lender treats the gap as risk shared rather than risk shifted. Presale cover on apartment projects commonly runs 60 to 100 percent of the senior debt, lighter or waived on townhouse and land projects. Lenders commonly re-run the feasibility on their own conservative end values and costs and want to see profit on cost in the high teens to low twenties after that haircut, so a sponsor's 25 percent margin can read as 19 in the lender's model. A construction contingency of at least around 5 percent of build cost is the common minimum, with experienced sponsors carrying more. And project size has a floor: small strips are hard to place because the legal and valuation costs do not shrink with the loan, and many mezzanine lenders prefer projects of several million dollars of total development cost and up.
The decline list is drawn from broking experience rather than lender marketing, and where this commonly lands is unglamorous: deals rarely die on the rate, they die on consent, cover and the builder. A developer who cannot get the senior lender to the intercreditor table has no mezzanine deal regardless of the project's margin, and a project whose equity gap exists because the sponsor has no cash at all, rather than cash committed elsewhere, reads as risk shifted rather than risk shared.
Can a small or first-time developer get mezzanine finance?
There is no universal minimum mezzanine loan in Australia. A $300,000 to $700,000 tranche may be too small for some specialist facilities once legal, valuation and intercreditor costs are considered. Others may consider smaller structures with additional property security or a stronger sponsor. Minimums from an individual provider are product rules, not a market-wide legal threshold. First-time developers may be considered on some projects, but experience, builder track record, cash reserves and the strength of the senior facility can become decisive.
Can you get mezzanine finance without presales or a DA?
No-presale construction funding is possible with some specialist lenders, but it is not a blanket mezzanine approval policy. Townhouse, apartment, subdivision and commercial projects can be assessed differently. Funding before a development approval may be land or pre-development finance rather than an ordinary construction-stage mezzanine tranche. An applicant should disclose the exact approval status and any senior lender presale covenants before seeking quotes.
| Situation | Most important lender question | Practical next step |
|---|---|---|
| $300k to $700k funding gap | Are deal size, legal costs and security enough to justify a second facility? | Compare a single stretched senior facility and alternative property security before commissioning legal documentation |
| First development | Who has delivered comparable projects, and who stands behind construction risk? | Provide the builder's and project manager's track records alongside the sponsor's equity evidence |
| DA not yet granted | Is this land/pre-development funding rather than construction mezzanine? | Separate pre-DA holding costs from the later construction funding proposal |
| No presales | Does the proposed senior and mezzanine lender combination accept this specific asset and location? | Request the presale requirement in writing from both lenders before relying on a quote |
| Subdivision or commercial project | How are valuation, staging and exit assessed for this asset? | Supply staged cashflow, approval conditions and the proposed sale or refinance exit |
Do not read these scenarios as offers or guaranteed eligibility. The decision turns on the actual term sheets and conditions precedent. A developer who cannot secure appropriate construction funding should examine whether the project needs more equity, a different senior lender, a revised development program or a smaller scope.
What can you negotiate on a mezzanine term sheet?
Seven terms on a mezzanine term sheet are commonly negotiable: the step-up rate, the minimum interest period, establishment fee staging, line fees, the guarantee cap, cross-default carve-outs, and consent and profit participation triggers. More is negotiable than first-time borrowers assume, and the wins compound because they repeat across every project. The rate is usually the least movable line on the page; the terms around the rate are where a prepared borrower, or their broker, earns the money back. Seven items come up on almost every deal, with the common market positions shown as indicative ranges as at July 2026.
- The step-up rate. Commonly 2 to 4 percentage points per annum added once the project runs past its target date. Push for a longer initial period, a softer step, or both; delays are the single most common way a mezzanine facility ends up costing more than modelled.
- The minimum interest period. Some lenders require a minimum-interest period even on early repayment; ask for the exact term and negotiate it if appropriate. On a project that settles fast, that difference is real money for one line of negotiation.
- Establishment fee staging. Some lenders seek an establishment fee at drawdown, with published indicative quotes varying by deal. Deferring part of it to settlement, or making it payable from proceeds, improves the project's working capital at no change to the headline cost.
- Line fees on the undrawn balance. Punitive on staged drawdowns. Where the lender insists, negotiate a fixed cap rather than a percentage that runs on money not yet borrowed.
- The guarantee cap. A directors' guarantee may be capped at a negotiated amount; an uncapped guarantee gives the lender a claim beyond the loan and should be resisted as a default setting, not accepted as one.
- Cross-default carve-outs. Multi-project sponsors should confine cross-default to this project's borrowing company and its senior facility, so a wobble on an unrelated project cannot detonate this one.
- Consent thresholds and any profit participation trigger. Blanket consent rights over variations slow a build; materiality thresholds are the fix. And where a profit kicker exists, the trigger margin is as negotiable as the percentage: a kicker that starts several points higher up the profit scale may simply never bite.
None of this list is exotic, and all of it is indicative: individual lenders hold firm on different lines. The pattern worth internalising is that a mezzanine lender prices the facility as a package, so a borrower who concedes the rate conversation quickly often has room on everything else. This is also, candidly, where a broker who sees mezzanine term sheets every month earns a place in the deal.
What happens if the project runs late or sales fall?
A construction delay increases accrued debt and can trigger extension charges just as the project's repayment date moves further away. Lower valuations or settlement delays reduce the cash available to repay senior debt first and mezzanine second. Model both timing and sales downside before agreeing to a short maturity or personal guarantees.
| Scenario | Interest on mezzanine | Principal plus accrued interest |
|---|---|---|
| Exit after 18 months | About $246,000 | About $1,046,000 |
| Exit after 24 months | About $344,000 | About $1,144,000 |
| Extra six months | About $98,000 more | About $98,000 more to repay |
The example assumes the entire principal is outstanding from day one, no repayments and no change in rate. In a real construction drawdown schedule the result may differ. The figures exclude establishment, extension, default and line fees, changes to senior debt interest, sales costs and tax. Those exclusions matter: default or step-up charges may make the delay materially more expensive.
What if completed homes sell for less than expected?
On an illustrative $7.5 million forecast gross realisation value, a 5% shortfall in sales proceeds is $375,000 and a 10% shortfall is $750,000. Neither figure is a prediction or a published default rate. Deduct selling expenses, senior debt payout and mezzanine principal plus accrued fees and interest before treating any balance as developer profit. A valuation shortfall can also affect refinance eligibility before a sale occurs.
What should the developer do before maturity?
Update the monthly cashflow and presale settlement schedule, get written payout estimates from both lenders, identify available extension and residual-stock terms, and ask the solicitor to review the deed's notice and cure periods. A refinance or extension needs lender approval; it is not a guaranteed escape route. Where the exit no longer repays both loans, discuss the shortfall promptly with the lenders and independent advisers rather than waiting for default.
What are the risks of mezzanine finance for the developer?
The main risks of mezzanine finance for a developer are compounding capitalised interest, cost and sales overruns landing on the dearest debt, presales that fail to settle, personal guarantees, lender control under the intercreditor deed, and gearing with no buffer. Mezzanine is leverage on leverage, so the fair question is not "is it dangerous" but "what exactly does it amplify". Used inside a sound feasibility it converts a stalled project into a running one. Used to paper over missing equity it magnifies every problem the project already had. These are the six risks that do the damage, with the numbers that make them concrete.
- Compounding cost against a fixed end value. Capitalised interest grows the debt every month while the project's end value does not move. On a $1 million strip at an indicative 18 percent capitalised monthly, six months of delay at the end of an 18-month program adds roughly $122,000 before any step-up rate; every month is repriced at the most expensive rate in the stack.
- Construction and sales risk landing on the dearest layer. Cost overruns and slow sales are absorbed by equity first, but they squeeze the mezzanine exit before they ever threaten the senior facility. Our note on development funding equity tiers in FY27 maps how thin the buffer can get at the top of the stack.
- Settlement risk on the exit. The facility's repayment assumes presales settle. Settlement failures can occur, particularly when buyers cannot complete or valuations and finance change; no reliable universal Australian default percentage is assumed here. A settlement shortfall pushes the exit into a residual stock refinance, commonly 60 to 70 percent of value in published ranges, cheaper than mezzanine but not instant to arrange.
- Personal guarantees that outlive the project company. A directors' guarantee reaches past the special purpose vehicle to the people behind it, so a shortfall on the project can follow the sponsors home. It is also usually the lender's fastest enforcement path, faster than realising the land.
- The lenders' deed runs the default. Standstill, cure rights, payment blocks and step-in mechanics in the intercreditor deed were negotiated between the lenders. In a default, the timetable is theirs, not the developer's.
- Gearing with no buffer. Combined debt near the top of the LVR range means a small fall in end value, or a valuation shortfall at refinance, can leave the stack owing more than the exit produces. The common discipline is to stress the feasibility at 5 and 10 percent below expected end value: a stack that cannot repay both facilities at minus 5 percent is carrying more mezzanine than the project can afford.
What happens if the mezzanine facility is not repaid at term end?
If the project has not repaid the mezzanine by the facility's end date, the lender's first tools are the step-up rate on the overdue balance and default interest under the loan terms. The usual ways out are a negotiated extension, which needs the senior lender's agreement under the intercreditor deed and normally carries a fee, or a residual stock loan over unsold stock that clears both facilities. If neither works, enforcement runs under the deed: the senior lender usually controls the timetable and the sale, receivers may be appointed over the project company, and the directors' guarantees can be called for any shortfall. With housing prices falling in late 2026, presale settlement shortfalls are the most likely trigger, so raising a likely overrun with both lenders early, while a refinance is still possible, keeps the most options open.
None of this argues against the instrument; it argues for using it on projects whose margin can carry it. A developer who prices the delay case, not just the base case, and who reads the intercreditor deed before signing rather than after defaulting, is using mezzanine the way it is designed to be used.
How is mezzanine finance regulated in Australia?
Mezzanine finance to a development company is not regulated as consumer credit: it is business-purpose commercial credit outside the National Credit Act, with the lowest level of borrower protection, while the regulators watch the private credit funds behind it. Business-purpose lending sits outside the National Consumer Credit Protection Act 2009: ASIC's guidance on whether the credit legislation applies puts the test at a predominant purpose, more than half consumer, and states plainly that loans to companies are not caught, which covers almost every development vehicle. Lenders typically document the position with a business purposes declaration, which is generally relied on unless the lender had reason to believe the funds were really for personal use. The narrow exception runs the other way: a loan to a natural person to buy or build residential property as an investment can still be regulated, which is one reason development borrowing is done through companies.
On the protection side, ASIC's guidance on disputes about commercial loans is blunt: the law provides the lowest level of protection to commercial loans, lenders who write only commercial loans need not hold a credit licence or belong to AFCA, and what remains are the ASIC Act's prohibitions on unconscionable and misleading conduct and unfair contract terms. For a mezzanine borrower the practical consequence is that the loan documents and the intercreditor deed are the protection, which is why specialist legal review is not optional. Wholesale investors funding these loans sit under a separate disclosure regime again, which is a fund question rather than a borrower one.
The market context explains the regulator's attention, and the numbers are worth seeing together.
What the RBA's October note means for a developer is double-edged: private credit remains where most mezzanine money comes from, and the regulators are now looking hard at how those funds value and manage stressed property loans, which a borrower can feel as tighter terms or a slower answer when a fund is under pressure. Closer scrutiny of the money behind the mezzanine layer is a reason to sharpen the feasibility, not to relax it.
Can mezzanine finance be used outside property development?
Yes: mezzanine finance also funds business acquisitions, management buyouts and growth capital, although property is where Australian mezzanine does most of its volume. In business lending, mezzanine sits between a senior facility and the owner's equity to fund acquisitions, management buyouts and growth capital: the same subordination, priced the same way, but leaning on the company's cash flow and enterprise value rather than a registered mortgage over land. This is the arena where the international, hybrid definition lives: corporate mezzanine more often carries an equity kicker such as warrants or a conversion right, and interest that can be paid in kind, accruing rather than paid in cash, which is why definitions written for that market read so differently from an Australian development term sheet. It suits an established business with reliable earnings that wants to fund a step change, buying a competitor, a premises or a large contract ramp-up, without selling ordinary equity to do it.
The eligibility logic transfers almost unchanged: a business case that survives the blended cost of debt, genuine owner skin in the deal, and a believable exit, here refinance out of trading cash flow rather than a sales schedule. One further practical point sits with the accountant rather than the lender: interest may be deductible where the borrowing is used for an eligible income-producing business purpose, but its treatment and timing, capitalisation, borrowing fees and GST outcomes require specific advice for the borrower and structure. For most owners the practical starting point is simpler than the label: map what the business needs against the whole menu on our business loans page, and if you are working through funding stages more broadly, the business owners finance hub and the government's guidance on applying for a business loan are both worth the read before any subordinated layer enters the conversation.
Mezzanine finance is the subordinated layer of a project's capital stack: a loan that sits behind senior debt and ahead of all equity, often supported by a second registered mortgage and agreed senior facility priority arrangements, commonly sized at 10 to 20 percent of total development cost and priced mid-teens to low twenties percent per annum with interest capitalised to the exit, every figure indicative. It exists to shrink the cash a developer contributes, it is governed between the lenders by an intercreditor deed, and it is commercial credit with the lowest level of borrower protection, inside a private credit market the regulators are watching on the fund side. Used on a project whose margin can carry the blended cost, it starts projects that would otherwise wait; used to replace equity that was never there, it amplifies everything that goes wrong. The funding conversation itself starts with development finance for your project.
Key takeaway: mezzanine is bought with three things, a consenting senior lender, a feasibility that survives the blended cost, and an exit you would bet the guarantees on. Price the delay case before you sign.What sources support this guide?
This guide is written from broking development and private credit deals, and primary regulatory information is distinguished here from published lender marketing ranges, illustrative maths and broker judgement. Published market prices may be stale and should never be treated as a live quote. The gearing, pricing, fee and eligibility ranges labelled as published market ranges are drawn from a survey of publicly available Australian development lending materials conducted on 8 July 2026, cross-checked against Switchboard's own deal flow and re-checked against published materials on 20 November 2026 after the November cash rate rise, and are indicative only; individual lenders publish outside every band. The decline patterns and negotiation positions are Switchboard's own broking experience, labelled as such rather than dressed up as statistics. The sources below are the ones the regulatory and market-size claims rest on.
For practical title-law questions, distinguish the state land registry's registration requirements from the senior loan contract's restrictions. A borrower should not treat registration as a substitute for lender approval.
- NSW Registrar General, electronic conveyancing webinar Q&A, and Switchboard's NSW second-mortgage explainer, for the distinction between registration mechanics and consent under a facility.
- Australian Taxation Office, borrowing expenses guidance and TR 2019/2; these help explain why borrowing costs and interest are not all automatically deductible in the same way or period.
- ASIC, Report 814, Australia's evolving capital markets (September 2025), for the private credit market estimate of around $200 billion, roughly half real estate focused, and the description of development lending as negative cash flow lending with a 36 to 60 month lifecycle.
- ASIC, Report 820, private credit surveillance report (November 2025), for the first review of 28 private credit funds, and Report 846 (November 2026), for the follow-up review of 24 funds and their combined assets.
- Reserve Bank of Australia, Financial Stability Review, resilience chapter (October 2026), for the non-bank share of financial system assets and private credit funds' exposure to stress in the property sector.
- Reserve Bank of Australia, Monetary Policy Decision, 3 November 2026, for the cash rate target of 4.85 percent, effective 4 November 2026, and the 11 August 2026 decision for the earlier 4.35 percent setting.
- APRA, quarterly ADI property exposures statistics, June 2026, for banks' commercial property exposures.
- ASIC, does the credit legislation apply and disputes about commercial loans, for the predominant purpose test, the business purposes declaration, the company exclusion and the level of protection on commercial loans.
- Australian Government, National Consumer Credit Protection Act 2009, the legislation the business-purpose boundary sits in, and business.gov.au on applying for a business loan for general business finance guidance.
Frequently Asked Questions
Mezzanine finance is a subordinated loan that sits between senior debt and the owner's equity in a funding structure. In Australian property development it tops up the senior construction facility, is usually secured by a second registered mortgage, prices well above senior debt, and is repaid after the senior lender when the project sells or refinances. In corporate lending the term often describes a hybrid instrument with an equity kicker such as warrants; the Australian property version is almost always straight secured debt. The name comes from its position in the capital stack: above equity, below senior debt.
In Australian property development, mezzanine finance is debt: a subordinated loan with a fixed rate, usually secured by a second registered mortgage and repaid before any equity. It is often described as a hybrid of debt and equity because corporate mezzanine can carry an equity kicker such as warrants or a conversion right, but the Australian property version is almost always straight secured debt. Preferred equity is the layer that behaves like equity.
It is added behind the senior construction facility to close the gap between what the senior lender will advance and the total project cost, so the developer contributes less cash. In indicative published Australian market ranges the mezzanine strip commonly runs 10 to 20 percent of total development cost, taking combined debt to roughly 75 to 90 percent of cost. Interest is usually capitalised to the facility, sometimes called rolled up interest, because a project under construction produces little or no income. The facility is repaid at the exit, from settlements as the completed stock sells or from a refinance, after the senior facility has been cleared. Our development finance guide covers the full structure.
Indicative published Australian ranges put development mezzanine at mid-teens to low twenties percent per annum, from around 12 percent for strong sponsors to the mid twenties or higher for weaker projects, plus establishment fees commonly 2 to 4 percent of the limit and sometimes a 2 to 5 percent profit share. These are published observations, not live offers. The RBA cash rate target became 4.85% on 4 November 2026, which does not move each mezzanine coupon mechanically, so compare written lender terms using projected dollar costs, drawn balances and exit timing.
Indicative published Australian ranges put the mezzanine strip at 10 to 20 percent of total development cost, taking combined senior and mezzanine debt to roughly 75 to 90 percent of cost and around 75 to 80 percent of end value. The actual amount is set by the senior lender's consent, genuine sponsor equity, presale cover, contingency and whether the feasibility survives a downside case, so these are not entitlements or approval thresholds. Ask for written terms on the specific project.
Typically a second-ranking registered mortgage over the project land, a general security agreement over the borrowing company registered on the PPSR, and personal or directors' guarantees, sometimes with share security over the development company. The senior lender's facility usually has to permit the second loan, and an intercreditor deed sets who ranks where. Title registration rules and the senior lender's contractual consent are separate questions, so have a solicitor review both before proceeding.
An intercreditor deed or deed of priority sets repayment ranking, payment restrictions, default notices, standstill periods, cure rights, further advances and enforcement arrangements between lenders. A senior construction lender normally wants agreed priority terms before permitting a subordinated facility. Registration of a later mortgage, which depends on state title law, is separate from the borrower's contractual obligations.
Mezzanine is debt: a subordinated loan with a fixed rate, usually secured by a second registered mortgage, repaid before any equity. Preferred equity is equity: no registered mortgage in most structures, a preferred return that often comes with a profit share, ranking behind all debt but ahead of the sponsor's own equity, and usually control rights such as step-in on default. They occupy a similar wedge in the capital stack but differ in legal nature, cost shape, security and exit; our note on preferred equity versus mezzanine compares them line by line.
No. Mezzanine finance is a subordinated funding layer, while a second mortgage is one possible form of security. Development mezzanine is commonly coordinated with the senior construction facility and intercreditor terms, whereas standalone second-mortgage loans can fund other purposes. Whether the senior lender permits borrowing and whether a title office registers a mortgage are separate questions.
At an indicative 18 percent per annum capitalised monthly, $1 million of mezzanine finance accrues about $196,000 over 12 months, about $307,000 over 18 months, and about $347,000 over 20 months before fees. Establishment fees, line fees, legal costs, valuation costs, step-ups and any profit participation can increase the all-in cost. These figures are illustrative only, not a quote, offer or approval indication.
Yes. Mezzanine loans also fund business acquisitions, management buyouts and growth capital, sitting between a senior facility and the owner's equity and priced for the subordinated risk. Corporate mezzanine more often carries the hybrid features the international definition describes: unsecured or lightly secured debt with an equity kicker such as warrants or conversion rights, and interest that can be paid in kind. It suits established businesses with reliable earnings that want to grow without giving up ordinary equity. Our business loans page maps where it sits among the alternatives.
Mezzanine finance in Australia comes from private credit funds, specialist non-bank lenders and private lenders such as family offices, rarely from banks. Most developers reach them through a broker who knows which lenders are writing second-ranking development debt, because the mezzanine has to be arranged alongside the senior facility and consented to by the senior lender. To get indicative terms quickly, have the development approval, feasibility, building contract or cost plan, presale schedule and the senior lender's term sheet ready.
Small mezzanine strips are harder to place, because the legal, valuation and intercreditor deed costs do not shrink with the loan, and many mezzanine lenders prefer projects of several million dollars of total development cost and up. On a smaller project, a stretched senior facility, a second mortgage over other property or a joint venture partner is often the more practical way to close the gap; our development finance guide compares them.
If the facility is not repaid at maturity, the lender can usually charge a step-up or default rate on the overdue balance. The common ways out are a negotiated extension, which normally needs the senior lender's agreement and carries a fee, or a residual stock loan over unsold stock to clear both facilities; neither is guaranteed. If those fail, enforcement runs under the intercreditor deed, the senior lender usually controls the sale, and guarantors can face shortfall claims. Get written payout figures and raise a likely overrun with both lenders before maturity.
Lenders commonly look for a development approval in place, genuine sponsor equity of around 10 to 15 percent of total development cost, a feasibility that still shows a high-teens to low-twenties profit on cost after their own re-run, presale cover that satisfies the senior lender, a fixed-price builder, a contingency of around 5 percent of build cost and a senior lender willing to consent. These are indicative market positions, not universal minimums, and no threshold guarantees approval, so ask each lender for its written criteria.
Mostly not as consumer credit. Business-purpose lending to a company falls outside the National Credit Act, and ASIC says commercial loans carry the lowest level of borrower protection, so lenders writing only commercial loans need not hold a credit licence or belong to AFCA. Scope can differ where the borrower is an individual. ASIC oversight of private credit funds does not create a borrower remedy, so the loan documents and intercreditor deed carry the weight; have them reviewed by a solicitor.
Mezzanine interest may be deductible if borrowed funds are applied to a qualifying income-producing or business purpose, but the deduction and timing depend on the borrower, use of funds and tax rules. Capitalised interest, establishment fees and the treatment of development property may have different consequences. A property-development accountant should review the actual structure; do not assume a uniform after-tax cost.
Main risks include capitalised interest increasing the payout, construction delays, cost overruns, weaker sales and failed presale settlements, limited refinancing options, personal guarantees and lender enforcement rights. Test a longer build and lower sales proceeds in the feasibility, request clear extension terms and confirm who controls enforcement under the intercreditor deed. A stress scenario is not a claim about the industry-wide frequency of defaults.
Peak debt is the maximum projected outstanding balance of the development loans during the project, after applicable drawdowns, capitalised interest and fees. Lenders may test it against both total development cost and gross realisation value. It can exceed the amount of principal originally approved or drawn, so the monthly funding model must show the debt peak and the money still required to finish construction.
Land equity may count where a lender accepts a defensible current land value and the sponsor genuinely owns the unencumbered value after existing debt and relevant transaction costs. A paper revaluation alone is not spendable cash. The lender may still require cash for construction costs, interest reserves, contingencies and completion.
Some non-bank lenders consider first-time developers or projects without presales, but conditions depend on project type, sponsor equity, building team and senior lender appetite. Funding before development approval is often treated as pre-development or land funding rather than ordinary construction mezzanine. No lender minimum or eligibility outcome applies across the entire market.
It depends on the project and the legal terms. Mezzanine has interest, fees and repayment obligations even if the project performs poorly; a genuine joint venture investor may share losses as well as profits, but takes an agreed share of upside and may gain control rights. Compare the developer’s after-finance cash profit, equity committed, guarantees and the result under delays and lower sales prices, not simply an interest rate against a profit-share percentage.