In the ACT the land is leased, so the first cost of a townhouse project can be a charge to change the lease. Here is how the lease variation charge works, how lenders budget for it, and the steps from lease variation to your first drawdown.
Quick Answer
Development finance in Canberra works much as it does elsewhere, with three ACT differences: the land is leasehold, not freehold; adding dwellings can trigger a lease variation charge; and lenders want that charge settled or funded before the first drawdown. The charge is only fixed once your DA is approved, so it starts as an estimate in your budget.
Also called: development loans ACT, construction finance Canberra. Construction finance is the narrower build facility; development finance also covers the site.
How does development finance work for a Canberra project on leasehold land?
Development finance for a Canberra project works the same way it does in any other city: a lender funds the site and the build in stages and sizes the facility against what the finished homes are worth. The difference is the land itself. In the ACT, land is generally held on a Crown lease, leasehold, not freehold, and the lease sets out what the block can be used for and how many dwellings it can carry.
The mechanics of the facility, from loan to cost through to the lender's view of gross realisation value, are the same ones set out in our property development finance guide and in how development finance works. How a Crown lease stands up as loan security is a separate question, covered in our second mortgage Canberra guide.
What changes in Canberra is the order of costs. If your project adds dwellings the current lease does not allow, the lease has to be varied, and varying it can trigger a lease variation charge before any construction money moves. That one line in the budget shapes the rest of the development finance conversation, so it is where this guide spends most of its time.
What is the lease variation charge and when do you pay it?
The lease variation charge is a charge the ACT Government levies when a Crown lease is varied so you can build or add development, and you pay it once the final amount has been assessed, which only happens after your development application is approved. The rules sit on the ACT Planning lease variation charge page.
The sequence matters for your loan. You lodge a DA that includes the lease variation. Until the DA is approved, the charge is an estimate. Once it is approved, a Notice of Assessment after DA approval sets the amount you owe. Only then does the true cost of the project lock in.
For a lender, that creates a gap between the feasibility you present at the start and the number that finally lands. On a two or three dwelling project the charge can be a large share of a small project's budget, which varies by site, so a lender wants to see how you have estimated it and where the money to pay it will come from.
How is the lease variation charge calculated on a townhouse or dual occupancy project?
The lease variation charge on a townhouse or dual occupancy project is calculated in one of two ways: a fixed amount looked up from a schedule, or an amount worked out from how much the variation lifts the value of the land. The ACT calls these codified and valuation-based charges.
- Codified variations (section 331). The charge is a fixed amount set out in the schedules to the ACT's current lease variation charges determination. Because the figure comes from a schedule, it can be estimated with some confidence before you lodge.
- Valuation-based variations (section 332). The charge is 75 per cent of the difference between the land's value after the variation and its value before, with improvements excluded. A valuer does this work, so the figure is harder to pin down early.
- The Missing Middle reduction. From 1 July 2026, a codified charge to add dwellings in an RZ1 or RZ2 zone may be halved, where the DA is approved before 30 June 2029, the charge is deferred through the ACT's deferral scheme, and the dwellings reach a Certificate of Occupancy and Use by 31 December 2030.
- The RZ1 dual occupancy waiver. A partial waiver is available for RZ1 blocks with an approved DA to unit title a dual occupancy.
Sources: ACT Government, Lease variation charge reduction for missing middle development, and ACT Revenue Office, RZ1 lease variation charge partial waiver, no page dates shown. Read 2 November 2026.
Which route your project falls into decides how early you can budget with confidence. We do not print dollar figures here because they depend on the site, the zone and the variation, and a planning consultant or valuer is the right person to estimate them for your block. Reductions and waivers change, so check what currently applies before you finalise the numbers.
How do lenders treat the lease variation charge in your budget and loan?
Lenders treat the lease variation charge as a project cost that must be paid or provided for before construction funds are released, and it is typically expected to come from your equity, although some lenders will include it in the funded costs, which varies by lender. The first question a lender asks is whether the full cost of the project, charge included, still leaves enough margin against the end value once everything is counted. The feasibility tests lenders apply are the same in Canberra; the charge is simply one more line they will want to see.
| Cost | When it falls due | Usually funded by |
|---|---|---|
| Site purchase | At settlement, before approvals if you buy first | Equity or a site acquisition loan |
| Design, planning and consultant fees | Before and during the DA | Typically equity |
| Lease variation charge | After DA approval, once the Notice of Assessment issues | Typically equity; some lenders fund it, varies by lender |
| Building approval and certifier fees | After the DA, before work starts | Typically equity |
| Construction | In stages as the build progresses | The development facility, paid against progress claims |
Sources: ACT Government, Lease variation charge, no page date shown. Read 2 November 2026. Funding columns are indicative broker observations, not ACT Government guidance.
If paying the charge in one hit strains your equity, ask the ACT Revenue Office whether the charge can be deferred for your project; on an RZ1 or RZ2 project, deferral is also the route to the Missing Middle reduction. We do not quote deferral terms because the ACT Government sets them and they depend on the project. The typical outcome is a lender approval that carries your estimate in the budget, a buffer for the difference, and a condition that the charge is settled or deferred on agreed terms before the first drawdown.
How long do ACT development and building approvals take before a lender will fund?
ACT approvals take as long as your DA and building approval take to clear, and a lender will not release construction funds until both are in hand, so the approvals set the timeline rather than the loan. How long that is depends on the size of the project, the quality of the application and whether it draws objections, so we do not quote day counts here. The smart move is to talk to a lender while the DA is being prepared, so the facility is ready when the approvals land. Our pre-construction development finance post covers funding the site in the meantime.
The ACT steps before your first drawdown usually run in this order:
- Check the lease. Confirm with a solicitor whether the lease purpose clause allows what you plan, or what variation is needed.
- Run the feasibility and sound out a lender. Include an estimate of the lease variation charge and get indicative terms early.
- Lodge the DA with the lease variation. Planning consultants usually prepare this for small projects.
- DA approval and the Notice of Assessment. The charge is now a known figure, and your budget can be finalised.
- Pay or settle the charge. Or confirm any deferral arrangement with the ACT Revenue Office.
- Building approval. A building certifier issues approval for the construction drawings.
- Lock in the builder. A fixed price contract in a form your lender will accept, set out in our guide to building contracts lenders accept.
- Meet the conditions and draw. The lender's cost review, insurances and documents are signed off, and the first drawdown goes ahead.
The document list for steps 7 and 8 is in our construction loan pack, and more builder and developer guides sit in the Construction Hub.
How do Canberra sales rates and land release affect presales and loan size?
Canberra sales rates and land release affect presales and loan size because a lender sizes the facility on what it expects the finished homes to sell for and how quickly they will sell. When new land is released in growth districts, buyers have more choice, and a valuation on townhouses in a nearby established suburb will reflect that competition. A cautious end value means a smaller facility for the same cost base.
That flows straight into presales. Larger facilities typically need a share of the homes sold off the plan before the build starts, and the contracts have to meet the lender's tests, which our qualifying presales guide sets out. Small projects can sometimes proceed with fewer or no presales where the developer's equity is stronger, which varies by lender.
The pattern is similar to other capitals, which you can compare in development finance in Sydney and NSW. For what lenders will lend against on a small multi-dwelling site, see funding two to six townhouses.
What does an ACT development lender need before the first drawdown?
An ACT development lender needs your approvals in place, a licensed builder on a signed contract, the right insurances, the lease variation charge paid or settled, and an independent cost review before the first drawdown. Anything still open on that list holds up the money.
Ready for first drawdown
- DA and building approval issued
- Lease varied and the charge paid or settled
- Builder licensed in the ACT, contract signed
- Building insurance in place where required
- Quantity surveyor report accepted by the lender
Still holding up the money
- Notice of Assessment not yet issued
- Charge unpaid with no agreed arrangement
- Builder quote but no signed contract
- Budget missing the charge or a contingency
- Lease purpose not confirmed by a solicitor
The cost review is usually done by a quantity surveyor the lender appoints, and our post on the quantity surveyor report explains what they test. Whether your lease purpose clause allows the use you plan, and how the variation is drafted, is a question for a solicitor; how the charge is treated for tax goes to your accountant.
Development finance in Canberra follows the national pattern, but the land is leasehold and adding dwellings can trigger a lease variation charge that is only fixed after DA approval. Lenders typically want it paid from equity or provided for in the budget, and they will not release construction funds until it is settled alongside your approvals, builder contract and cost review.
Key takeaway: put an early estimate of the lease variation charge in your feasibility, and talk to a broker before you lodge the DA so the facility is ready when the Notice of Assessment arrives.Frequently Asked Questions
You can get development finance in Canberra for a dual occupancy, provided the Crown lease allows the second dwelling or can be varied to allow it, and the numbers work against the finished value. Lenders look at the approved DA, any lease variation charge and how much equity you bring before they set terms. On a two dwelling project the gap between cost and valuation is the usual sticking point, which we cover in duplex development finance and the valuation gap.
The lease variation charge on a dual occupancy depends on whether the variation is codified, with a fixed amount set in a schedule, or valuation-based, worked out at 75 per cent of the lift in land value. From 1 July 2026 a codified charge to add dwellings in RZ1 or RZ2 may be halved under the ACT's Missing Middle reduction, and RZ1 blocks with an approved DA to unit title a dual occupancy may qualify for a partial waiver. The final figure arrives in the Notice of Assessment after DA approval, so budget an estimate from your consultant and confirm it against the valuation work behind it.
Lenders do fund development on ACT leasehold land, because a Crown lease is the normal form of title in Canberra. What they check is that the lease purpose allows the project, that any variation is approved and that the charge is settled or provided for. How a Crown lease works as loan security is covered in our second mortgage Canberra guide.
The lease variation charge is paid after the DA, because the final amount is not set until the development application is approved and a Notice of Assessment issues. Before that you are working from an estimate, which is why lenders often approve a facility subject to the charge being settled. Funding the site while approvals run is covered in our pre-construction development finance post.
You may need presales for a townhouse development in Canberra, depending on the number of dwellings, the loan amount and the lender. Larger facilities typically require a share of the homes sold off the plan, while smaller projects can sometimes proceed on stronger equity, which varies by lender. Our qualifying presales guide explains which contracts a lender will count.